LAS SHIELD LAS

Force Majeure in Thai Law — When Can You Invoke It? (Complete Guide) ✓

✓ Legal content last reviewed 29 September 2026 · synced with the audited Thai edition

Thundthornthep Yamoutai, Ph.D. | LAS Legal | Published 3 April 2026 | Last updated 28 September 2026 | ภาษาไทย

Floods, earthquakes, pandemics, wars — these events can make contractual performance impossible. What does Thai law say? Force Majeure, or "het sut wisat" (เหตุสุดวิสัย), is a legal doctrine every business operator must understand. It can serve as a shield or become a trap, depending on whether it is invoked correctly and whether a well-drafted FM clause was in place from the outset.

This article covers: the definition and elements under Thai law (TCCC Section 219), COVID-19 lessons, how to draft a proper FM clause, the notification procedure, and the distinctions from Hardship and Frustration. It also sets the statutory test in Sections 8 and 219 beside a Supreme Court decision on force majeure, and works through three illustrative business scenarios.

Table of Contents
  1. Definition of "Force Majeure" — TCCC Section 8
  2. Elements That Must Be Proven
  3. Legal Consequences — Sections 219 and 372
  4. COVID-19 and Force Majeure in Thailand
  5. FM vs Hardship vs Frustration
  6. How to Draft a Force Majeure Clause
  7. Notification Procedure
  8. Consequences of a Successful FM Claim
  9. Force Majeure vs MAC/MAE
  10. Thai Court Approach
  11. The Statute and a Supreme Court Decision
  12. Illustrative Case Studies — 3 Business Scenarios
  13. FM Clause Drafting Checklist — 10 Points
  14. Suspension vs Termination
  15. Force Majeure in International Contracts
  16. LAS Practical Guide
  17. LAS Risk Assessment
  18. Frequently Asked Questions (FAQ)

Definition of "Force Majeure" — TCCC Section 8

ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา ๘ · PDF Civil and Commercial Code
      มาตรา ๘  คำว่า “เหตุสุดวิสัย” หมายความว่า เหตุใด ๆ อันจะเกิดขึ้นก็ดี จะให้ผลพิบัติก็ดี เป็นเหตุที่ไม่อาจป้องกันได้แม้ทั้งบุคคลผู้ต้องประสบหรือใกล้จะต้องประสบเหตุนั้น จะได้จัดการระมัดระวังตามสมควรอันพึงคาดหมายได้จากบุคคลในฐานะและภาวะเช่นนั้น

The box above is the Thai text of ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา ๘ from the official PDF. The English sentence after this is a lecture, not the statute.

Key Words in the Definition

Examples Recognized as Force Majeure Under Thai Law and Court Decisions

Examples That Do NOT Qualify as Force Majeure

Elements That Must Be Proven

To successfully invoke force majeure under Thai law, the invoking party must prove four elements:

#ElementDescriptionExample Evidence
1UnforeseeableThe event could not have been predicted at the time the contract was madeOfficial announcements, news reports
2IrresistibleEven with reasonable precautions, the event could not have been preventedEvidence of mitigation attempts
3Not the Party's FaultThe invoking party did not cause the eventTimeline of events
4Causal LinkThe event directly caused the inability to perform the contractual obligationDirect link between cause and non-performance

Section 219 — Obligation Becomes Impossible

ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา ๒๑๙ · PDF Civil and Commercial Code
      มาตรา ๒๑๙  ถ้าการชำระหนี้กลายเป็นพ้นวิสัยเพราะพฤติการณ์อันใดอันหนึ่งซึ่งเกิดขึ้นภายหลังที่ได้ก่อหนี้ และซึ่งลูกหนี้ไม่ต้องรับผิดชอบนั้นไซร้ ท่านว่าลูกหนี้เป็นอันหลุดพ้นจากการชำระหนี้นั้น

      ถ้าภายหลังที่ได้ก่อหนี้ขึ้นแล้วนั้น ลูกหนี้กลายเป็นคนไม่สามารถจะชำระหนี้ได้ไซร้ ท่านให้ถือเสมือนว่าเป็นพฤติการณ์ที่ทำให้การชำระหนี้ตกเป็นอันพ้นวิสัยฉะนั้น

The box above is ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา ๒๑๙ from the official PDF. Read both paragraphs in the box.

That is, if force majeure makes performance entirely impossible, the obligor is discharged — no obligation to perform and no liability for damages.

Critical Point: "Impossible" Is Not "More Difficult"

🔴 Risk: High — Wrong Type of FM Claim

Section 219 requires Impossibility, not mere difficulty or increased cost. If there is still some way to perform, even at greater expense, the obligation is not impossible under TCCC Section 219. An FM claim without proof of true impossibility will be rejected, and the invoking party will remain liable for breach of contract. Option A: Before invoking FM, evaluate whether any alternative means of performance exist. | Option B: Consult legal counsel to assess the strength of the FM argument before making any claim.

Section 372 — Synallagmatic (Bilateral) Contracts

TCCC Section 372 provides that in a synallagmatic contract, if performance becomes impossible for a reason not attributable to the obligor, the obligor loses the right to claim counter-performance. In other words:

Section 220 — Liability for Agents and Helpers

ประมวลกฎหมายแพ่งและพาณิชย์ มาตรา ๒๒๐ · PDF ประมวลกฎหมายแพ่งและพาณิชย์
      มาตรา ๒๒๐  ลูกหนี้ต้องรับผิดชอบในความผิดของตัวแทนแห่งตนกับทั้งของบุคคลทตนใช้ในการชำระหนี้นั้นโดยขนาดเสมอกับว่าเป็นความผิดของตนเองฉะนั้น แต่บทบัญญัติแห่งมาตรา ๓๗๓ หาใช้บังคับแก่กรณีเช่นนี้ด้วยไม่

Read มาตรา ๒๒๐ in the box. The statutory Thai text is the PDF. English on this page is a reading aid.

TCCC Section 220 makes the obligor responsible for the fault of its agents and persons used to perform the obligation as if it were its own fault. It does not prescribe the burden of proving force majeure. A party relying on an extraordinary event should preserve evidence of the event, its effect on performance and the steps taken.

COVID-19 and Force Majeure in Thailand — Key Lessons

The COVID-19 pandemic during 2020–2022 generated a large number of FM disputes in Thailand. The key lessons from this period are as follows.

Situations Where FM Was Accepted

Situations Where FM Was NOT Accepted

ScenarioFM Accepted?Reason
Restaurant ordered closed by EOCYesImpossible to provide service at all (Impossibility)
Restaurant open but fewer customersNoStill operational; revenue reduced only (Difficulty)
Event space lease — event cancelledPossiblyDepends whether government order directly prohibited the event
Export contract — all flights cancelledYesNo transportation route remaining whatsoever
Construction contract — cost up 50% due to COVIDNoConstruction still possible but more expensive — Hardship, not FM

Six Lessons from COVID-19 to Build Into Every New Contract

#LessonWhat to Add to the Contract
1Many contracts had no mention of pandemics in their FM clauseAdd "Pandemic, Epidemic, Government-mandated Closure" to the FM list
2Multi-layered government orders (EOC + Emergency Decree) made interpretation difficultSpecify "any order of any competent government authority" constitutes FM
3Disputes over event venue and hotel contracts were extremely commonAdd explicit FM provisions to Deposit/Cancellation policies
4Supply chain disruption did not generally qualify as FMAdd a Supply Chain Disruption Clause or Alternative Sourcing Provision
5Parties did not know how to notify FM; notices were late or incompleteDefine the FM notification procedure clearly, with a template notice letter
6After the crisis, parties did not know what to do nextAdd provisions for Resume of Performance and Extension of Time

Force Majeure vs Hardship vs Frustration

IssueForce Majeure (FM)Hardship (Changed Circumstances)Frustration (Common Law)
ImpactPerformance entirely impossiblePerformance possible but excessively onerousThe purpose of the contract is defeated
Legal systemCivil Law + ContractThai contract terms; no general Section 388 adjustment ruleCommon Law (England)
Legal consequenceDischarge from obligationRenegotiation or adjustment if the parties agree or another applicable basis is establishedContract automatically terminated
Statutory referenceTCCC Sec. 8, 219, 372No general TCCC Section 388 hardship remedyNo direct equivalent in Thai law
ExampleFactory flooded — goods cannot be deliveredSteel price up 300% — construction still possibleFlowers ordered for coronation — event cancelled

Section 388 — Essential Fixed-Time Termination, Not Hardship

TCCC Section 388 concerns termination without the preceding notice when the parties make performance by a specified time essential and that time passes without performance. It does not make a contract void for initial impossibility or give a general right to judicial adjustment because performance became more expensive. Parties should address cost escalation and renegotiation expressly in their agreement.

How to Draft a Force Majeure Clause

A well-drafted FM clause ensures both parties know in advance what happens when an FM event occurs, minimising disputes.

Structure of a Complete FM Clause

Force Majeure Clause — Template

Clause [__]. Force Majeure

[__].1 Definition: "Force Majeure" means any event or circumstance beyond the reasonable control of either Party, including but not limited to natural disasters, floods, earthquakes, storms, pandemics, widespread power outages, war, terrorism, declarations of states of emergency, or any order or prohibition by any government authority having legal competence, which prevents the affected Party from performing its obligations under this Agreement.

[__].2 Effect of Force Majeure: If either Party is unable to perform any obligation under this Agreement as a direct result of a Force Majeure event, that Party shall not be liable for such non-performance for so long as the Force Majeure event continues.

[__].3 Duty to Notify: The Party affected by Force Majeure shall give written notice to the other Party immediately, and in any event no later than [5/7/14] business days from the date the affected Party became aware or should have become aware of the Force Majeure event.

[__].4 Duty to Mitigate: The Party invoking Force Majeure shall take all reasonable measures to mitigate the effects of the Force Majeure event and shall take steps to resume performance of its obligations as soon as reasonably practicable.

[__].5 Maximum Duration: If the Force Majeure event continues for more than [30/60/90] consecutive days, either Party shall have the right to terminate this Agreement by giving written notice of [5/7] days.

Key Pitfalls in Drafting the FM Clause

Notification Procedure When Force Majeure Occurs

When an event that may constitute Force Majeure occurs, the following steps must be taken immediately:

  1. Assess whether the elements of FM are met: Before invoking FM, confirm that performance is truly impossible — not merely harder. If uncertain, consult legal counsel first.
  2. Notify the other party immediately: Send a written notice complying with the FM clause requirements. If the contract contains no notice requirement, notify promptly.
  3. Include key information in the notice: (1) Nature of the event; (2) Expected duration; (3) Specific obligations affected; (4) Mitigation measures being taken.
  4. Preserve evidence: Official announcements, news reports, photographs, internal records — everything that proves the event occurred and directly affected performance.
  5. Take mitigation measures: Document all steps taken to reduce impact — finding alternative suppliers, rerouting deliveries, adjusting work methods.
  6. Monitor and report progress: Keep the other party informed as the situation evolves.
🟡 Risk: Medium — Late FM Notice

If the contract specifies a notice period and notice is not given in time, the other party may argue that the right to invoke FM has been waived, even if the underlying event would otherwise qualify. Always notify as soon as the event is known — do not wait until the full impact is clear.

Consequences of a Successful FM Claim

ScenarioLegal ConsequenceParties' Rights
Temporary FMPerformance suspendedMust resume performance when FM ends
Permanent FMObligation discharged — TCCC Sec. 219Contract terminates; neither party liable
FM exceeds contractual maximum durationRight of termination arisesEither party may terminate by notice
Advance payment made; permanent FM occursMay be required to return payment (unjust enrichment)Per TCCC Sec. 406–419

Force Majeure vs MAC/MAE — Important Distinction in Business Contracts

In M&A transactions, mergers, or large credit agreements, both Force Majeure Clauses and Material Adverse Change (MAC) / Material Adverse Effect (MAE) Clauses often appear. They serve similar functions but have important differences.

IssueForce Majeure (FM)Material Adverse Change (MAC) / Material Adverse Effect (MAE)
PurposeDischarge performance obligation when impossibleGrant a right to exit the deal when a significant change occurs
Trigger conditionTrue impossibility of performanceA materially adverse change (even if performance remains possible)
Legal consequenceSuspension or dischargeRight to terminate / walk away from deal
Used inGeneral commercial, service, and construction contractsM&A SPAs, financing agreements, share purchase agreements, credit facilities
Burden of proofParty invoking FM must proveParty invoking MAC/MAE must prove the change is material
ExampleFactory flooded — delivery impossibleTarget company in M&A loses 40% revenue before deal closes
Important Note: In international M&A contracts (particularly those governed by Delaware or English law), MAE clauses generate the most litigation because the term "Material" has no fixed definition. Under Thai law, which has no direct MAE provision, any MAE clause must be carefully defined in the contract itself.

Thai Court Approach to Force Majeure

Principle 1 — "Impossible" Means Truly Impossible

Thai courts interpret "impossible" (พ้นวิสัย) strictly under TCCC Section 219. It means the obligor cannot perform at all — not merely that performance became harder or more expensive. If there is any way to perform, even at higher cost, the obligation is not "impossible."

Principle 2 — Burden of Proof Falls on the Invoking Party

The party relying on force majeure should substantiate the event, its causal effect on the particular obligation and the precautions taken. Section 220 addresses fault of agents and helpers; it is not the statutory basis for this proof checklist.

Principle 3 — Timeliness of Notice Matters

Sections 8 and 219 of the TCCC do not set any duty or period for notifying force majeure. The notice period, the form of notice and the effect of late notice therefore depend mainly on the contract: the parties should state them clearly, and the affected party should give notice promptly and keep evidence that it did so.

Principle 4 — Foreseeable Events Cannot Be FM

If the parties entered the contract knowing that the relevant event had already occurred (e.g., contracting during an active COVID outbreak), courts generally will not accept an FM claim for that event, since it was already foreseeable.

The Statute and a Supreme Court Decision on Force Majeure

The table below sets TCCC Sections 8 and 219 beside Supreme Court Decision No. 6405/2538 to show how the force majeure test works in practice.

SourceIssueRuling or Statutory Rule
Statute — Section 8Definition of force majeureThe event must be one that could not be prevented even if the person affected, or about to be affected, had taken the care reasonably expected of a person in that position and circumstances (TCCC Section 8). A storm or heavy sea alone is not enough; the party must also show that such care was taken.
Supreme Court Decision No. 6405/2538Goods damaged in a storm during transitStorm occurred, but carrier failed to prove it had taken reasonable preventive measures — FM rejected; carrier remained liable
Statute — Section 219Performance becomes impossibleThe obligor is released only where performance becomes impossible through a circumstance arising after the obligation was created for which the obligor is not responsible (TCCC Section 219). If the obligor is responsible for the circumstance, it is not released under this section.
Key Pattern from the Statute and the Decision Above: A party invoking force majeure must show both (1) that the event occurred and (2) that it took the care reasonably expected of a person in its position and circumstances but still could not prevent the harm (TCCC Section 8). In Supreme Court Decision No. 6405/2538 the court rejected a carrier's plea because the carrier could not prove that it had taken preventive measures. Proving the event alone is not enough.

Illustrative Case Studies — 3 Business Scenarios

The three cases below are hypothetical examples used to explain legal principles; they are not actual court judgments.

Case 1: COVID-19 Lockdown — Shopping Mall Lease (Company A)

Company A leased retail space in a shopping mall. The EOC issued an order closing all shopping malls under the Emergency Decree. Company A could not open its store at all for two months.

Case 2: 2011 Great Flood — Goods Delivery Contract (Company B)

Company B contracted to deliver machinery to a buyer's factory. The 2011 flood inundated major transportation routes and the buyer's factory itself for three months.

Case 3: Construction Cost Escalation — Illustrative Scenario (Company C)

Company C, a construction contractor, invoked FM due to COVID-19, claiming that increased costs and supply chain disruptions made the project impossible to complete on time.

FM Clause Drafting Checklist — 10 Points

Before signing any contract with a Force Majeure clause, verify these 10 points:

  1. List specific events: Include storm, flood, COVID-19, pandemic, epidemic, government emergency decree, and cyberattack. Do not rely solely on a vague catch-all.
  2. Written notice within 7 days: Specify the notice period explicitly — recommended 5–7 business days from the date the FM event is known. Require written notice.
  3. Define mitigation obligations: The invoking party must take all reasonable steps to limit the impact. Failure to mitigate can defeat an FM claim.
  4. Specify consequences clearly: State whether FM results in (a) a time extension, (b) rent or price reduction, or (c) a right to terminate. Ambiguity leads to disputes.
  5. Include proof requirements: List the documents required to substantiate an FM claim — official orders, news reports, photographs, expert statements.
  6. "Inconvenience" is not FM: Expressly state that increased cost, reduced revenue, or market inconvenience does not constitute force majeure.
  7. Add governing law and dispute resolution: Specify Thai law or international arbitration rules. Critical for cross-border contracts.
  8. Review annually: FM clauses should be reviewed each year, particularly after emerging risk events (pandemics, geopolitical crises) to ensure coverage remains appropriate.
  9. Consistency with insurance policies: Verify that the FM clause in the contract aligns with the coverage under the party's business interruption or cargo insurance policy.
  10. Lawyer review before signing: For contracts with significant financial exposure, have counsel review the FM clause against applicable Thai law and the specific nature of the transaction.
🔴 Risk: High — Overly Broad FM Clause Without Limits

FM clauses that use language such as "any event beyond a party's control" without further definition create an open door for a party seeking to avoid its obligations to invoke FM in almost any circumstance. Option A: Use an Inclusive List approach — enumerate specific FM events, then add a general catch-all with a qualifying condition (e.g., "events of comparable severity and beyond reasonable control"). | Option B: Add express carve-outs: "Financial difficulty, change in market conditions, and increase in costs shall not constitute Force Majeure."

Suspension vs Termination — The Critical Distinction

When FM is successfully invoked, the legal consequence is either Suspension (temporary deferral) or Termination (permanent ending of the contract), depending on the nature of the event and the contract's terms. These have very different implications.

Suspension — Temporary Deferral of Performance

Termination — Permanent Ending of the Contract Due to FM

IssueSuspensionTermination
Is the contract still in force?Yes — merely deferredNo — ended
Must performance resume?Yes, when FM endsNo
Payments already madeAdjusted for work doneMay need partial refund
Notice required?Notice of FM and expected durationExpress termination notice
Appropriate forTemporary FM expected to endPermanent or prolonged FM
🟡 Risk: Medium — No Timeline for Converting Suspension to Termination

Many contracts state that FM suspends performance, but do not specify when a party may terminate if FM persists. This leaves the non-affected party waiting indefinitely. Option A: Specify clearly: "If FM continues for more than 90 consecutive days, either Party shall have the right to terminate by written notice." | Option B: Add a Hardship Renegotiation Period before the right to terminate arises.

Force Majeure in International Contracts — ICC 2020 Standard

For contracts with foreign counterparties, the International Chamber of Commerce (ICC) has published the ICC Force Majeure Clause 2020 as a reference standard. This clause is more comprehensive than relying solely on statutory Thai law. If adopted, it should be adapted to align with Thai law and the parties should agree on specific notice periods. It is particularly recommended in construction contracts, EPC agreements, and international sale of goods contracts. Invoking an internationally recognised FM standard reduces disputes in international arbitration. UNIDROIT Principles 2016 Article 7.1.7 is another reference standard used where the parties choose general principles of law rather than a specific national law.

LAS Practical Guide — What To Do When an FM Event Occurs

  1. Assess the situation within 24–48 hours: Is performance truly impossible, or merely harder? If merely harder — FM will not succeed; find a way to perform.
  2. Read the FM clause in full: Check the definition, the list of events, the notice period, the required form of notice, and the stated consequences.
  3. Preserve evidence immediately: Official proclamations, news reports, photographs, internal records — everything that proves the event occurred and directly affected your ability to perform.
  4. Send the notice within the required period: Do not wait for the situation to become fully clear before notifying — notify immediately and state that you will provide further updates.
  5. Take mitigation measures and document them: Show that every reasonable alternative was explored — alternative suppliers, alternative routes, modified work methods.
  6. Consult legal counsel: Especially for high-value contracts — assess the strength of the FM claim and prepare a negotiation strategy before making a formal claim.
🟢 Best Practice — Establish an FM Response Team in Advance

Organisations with multiple significant contracts should establish an FM response plan before any crisis arises: designate responsible personnel, prepare a template FM notice letter, maintain an FM register for key contracts, and run a drill annually. Advance preparation reduces response time and prevents loss of rights through late notification.

LAS Risk Assessment — Force Majeure

ScenarioRisk LevelRecommendation
Contract contains no FM clause whatsoever🔴 HighMust rely on TCCC Sec. 219 directly — elements are strict and burden of proof is heavy
Invoking FM due to increased costs alone🔴 HighCourts will reject — party remains fully liable for damages
FM clause is overly broad, without defined limits🔴 HighCounterparty may invoke FM in almost any circumstance
FM clause does not specify a notice period🟡 MediumNotify immediately; document date and method of notification
FM clause has no maximum duration provision🟡 MediumBoth parties may be left waiting indefinitely
FM clause in main contract inconsistent with sub-contracts🟡 MediumReview and align before signing
Complete FM clause in place; procedure properly followed🟢 LowLow risk — still must prove the FM event actually occurred and was unavoidable

Frequently Asked Questions (FAQ)

Q1: If a contract has no Force Majeure clause, can FM still be invoked under Thai law?
Yes. Even without a contractual FM clause, a party unable to perform may invoke TCCC Section 219 directly. However, all elements under TCCC Section 8 must be fully proven — which is significantly harder without a clear contractual FM framework. A well-drafted FM clause reduces uncertainty and provides an agreed procedure for both parties.
Q2: Must Force Majeure always be notified in writing?
Thai law does not specify a mandatory form for FM notification. However, written notice is strongly recommended in all cases, to create evidence of the date and content of the notification. If the contract specifies a form of notice (e.g., written, by registered mail, or email to a designated address), that form must be strictly followed.
Q3: How much mitigation effort is required from the party invoking FM?
The standard is "reasonable" effort under TCCC Section 8 — "reasonable care as may be expected from a person in the same situation." The invoking party must demonstrate that it explored all reasonable alternatives, such as finding alternative suppliers, rerouting delivery, or modifying work methods. Simply waiting passively is not sufficient.
Q4: In an international contract governed by Thai law, how does Thai Force Majeure differ from Common Law?
Key differences: Thai Civil Law defines "force majeure" by statute (TCCC Sec. 8), focusing on impossibility of performance. Common Law uses the doctrine of "Frustration," which focuses on the destruction of the contractual purpose — a broader concept. In international contracts, a self-contained, well-defined FM clause is always preferable to relying on either statutory default, since the parties control the scope and procedure.
Q5: When FM ends, must performance resume immediately?
When FM ends, the affected party must notify the other party and resume performance within a reasonable time. If the contract specifies a recovery period, that period governs. Where FM has caused the contract to run late, the parties should agree on an extension of time proportional to the FM duration.
Q6 (Bonus): If a contract expressly states "Pandemic is not Force Majeure," is that clause valid under Thai law?
In principle, yes. Parties in commercial contracts are free to contract under the general principle of freedom of contract and TCCC Section 151, and may agree to exclude particular events from the FM definition. However, if such a clause violates public order or is used in a consumer contract where bargaining power is unequal, a court may decline to enforce it. In practice, such clauses between business operators are generally enforceable.
Q7: Can extreme heat, drought, or climate-related events qualify as force majeure under Thai law?
Yes, in principle — if the party can prove the event was unforeseeable and unpreventable under TCCC Section 8. However, the standard requires that the event was extraordinary and went beyond what could reasonably have been anticipated for the relevant area and season. A national drought emergency declaration or a government order restricting operations due to extreme weather would strengthen such a claim significantly. Routine seasonal drought in an area where it is a recurring risk will generally not qualify.
Q8: Can economic sanctions imposed by a foreign government qualify as force majeure in a Thai contract?
Yes, if the contract's FM clause includes "government action" or "sanctions" as listed events, or if the sanction makes performance illegal or truly impossible. For example, a sanction prohibiting export of specific goods to a particular country would make the seller's delivery obligation legally impossible. In international contracts governed by Thai law, it is strongly recommended to expressly list "sanctions," "export restrictions," and "acts of a foreign government" as FM events to avoid disputes about whether they fall within a generic FM definition.

Summary

Force Majeure is not a ready-made excuse usable in every difficult situation. All elements under TCCC Section 8 must be satisfied — in particular, the event must create true impossibility, not merely hardship or difficulty. The COVID-19 experience demonstrated that a clear, well-drafted FM clause — defining the FM events, the notification procedure, the legal consequences, and the maximum duration — is the best way to prevent unnecessary disputes. The LAS Shield principle: prepare the FM clause before the crisis occurs, not after it arrives.

Read more: LAS Shield Part 7 — Warranty vs Guarantee Under Thai Law

← Part 5 (Thai version) LAS SHIELD 6/10 Part 7 →

Disclaimer: This article is prepared for academic and general informational purposes only. It does not constitute legal advice for any specific situation. Readers should consult qualified legal counsel before taking any legal action. | บทความนี้จัดทำเพื่อวัตถุประสงค์ทางวิชาการและให้ความรู้ทั่วไปเท่านั้น ไม่ถือเป็นคำแนะนำทางกฎหมายเฉพาะราย